It is the responsibility of either the contractor or owner to schedule inspections.  Please try to give us as much notice as possible.  Copies of all inspections are kept in the Building Inspection office.  If at any time you would like to view or receive a copy, stop by our office. 

The inspection schedule is as follows:

1) Footers - before they are poured.
2) Temporary Electric - we have to approve (green tag) before meter will be installed.
3) Before Walls are Covered - we look at electric, plumbing, and framing before any insulation or drywall is hung.
4) Final (Certificate of Occupancy if Required).

* Remember, we are here to help you.  Always call if you are not sure of codes, procedures, etc.  Additional inspections are always acceptable.  We know that situations occur where a day's notice for inspections, etc., cannot be given.  We are always willing to work with you.